Skip to main content

Templeton Area Redevelopment Update

Construction Activities: Two Week Period of September 27-October 8, 2021

Landscaping and miscellaneous small concrete work continue over the next two weeks. Learn about what to expect during construction here. This week’s update, which covers the next two weeks follows below. There is no scheduled update the week of October 4.

OVERVIEW (new activity this period)

Landscaping and irrigation installations continue as construction winds down, with target completion mid-October. Pedestrian bridge installation also will take place toward the end of this period. For notice of specific activities over the next two weeks, please see detailed update below.

If you have questions about the project and would like to connect with our community liaison Pam by phone or in person, please email to [email protected] or call/text 604-561-2836.

SEPTEMBER 27- OCTOBER 8, 2021: WHAT YOU CAN EXPECT 

Areas of focus over the next two weeks include:

New work:

  • Install pedestrian bridge walking surfaces.

Continuing:

  • Place topsoil (80% complete).
  • Install irrigation (50% complete).
  • Excavate areas where the new thicket will be planted (15% complete).
  • Line painting.
  • Miscellaneous small concrete work.
  • Dust monitoring and watering as necessary.
  • Vehicles and equipment moving throughout the site.

Onsite equipment includes excavators, backhoe loaders, haul trucks, compacting equipment, and a forklift. Broadband travel alarms are in use on regularly stationed equipment to reduce noise. Traditional tonal alarms continue to be used on equipment that travels to/from the site or will be onsite for shorter durations.

HOURS OF OPERATION & SCHEDULED ACTIVITIES (no new updates)

Construction takes place Monday through Friday from 7 a.m. to 6 p.m. daily. Equipment and machinery are turned on after 7:30 a.m. An update will be provided if work is required outside of this timeframe.

Please note plans, activities and onsite equipment are subject to change based on evolving project needs and weather.

NEED MORE INFORMATION? 

If you have any questions or comments about construction-related activities or would like to sign up to receive weekly updates by email, please contact [email protected].

Check out previous construction updates here.

For more information or general questions about the Templeton Area Redevelopment Project, please visit yvr.ca/templeton.

We use cookies to improve user experience, and by using this site, you consent to the use of cookies. Learn more and how to manage your preferences on our Privacy page.