Templeton Area Redevelopment Update

Construction Activities: Two Week Period of November 22 to December 3, 2021

Landscaping and tree-planting continue to be the key activities over the next two weeks. Learn about what to expect during construction here. This week’s update, which covers the next two weeks follows below. There is no scheduled update the week of November 29.

We also want to draw your attention to a few enquiries that arose last week and YVR’s response:

  • On Sunday, November 14, as much of B.C.’s lower mainland experienced an atmospheric river event, parts of Burkeville, including the laneway behind Wellington Crescent partially flooded. On receipt of concerns from some of our Wellington Crescent neighbors, YVR coordinated with the City of Richmond to support a response, including arranging for our construction contractor to pump away the excess water the next day. The Burkeville area has a history of flooding at times during the rainy season, and in the past, excess water from Burkeville has drained into YVR lands. This is a long-standing challenge, which the City is working to address. YVR is supporting by working with the City to support a longer-term solution, with more details to come.
  • A new CCTV security camera has been installed near the intersection of Templeton Street and the Terrace Street extension, which will monitor the access gate for YVR operational staff in case they have difficulty manually opening the gate. The camera is directed so that the camera view does not extend to the laneway or any Burkeville residential properties. Please visit our website for more information about YVR’s privacy policy.

OVERVIEW (new activity this period)

Landscaping and tree planting to compete the meadow areas continue as construction winds down. For notice of specific activities related to the Templeton Project over the next two weeks, please see detailed update below.

If you have questions about the project and would like to connect with our community liaison Pam by phone or in person, please email to [email protected] or call/text 604-561-2836.

NOVEMBER 22-DECEMBER 3 2021: WHAT YOU CAN EXPECT 

Areas of focus over the next two weeks include:

New work:

  • Remove utilities along Edwards Street at the west end of the construction site, parallel to the south end of Wellington Crescent (not noisy).

Continuing:

  • Place topsoil and hydroseed. Depending on weather, limited planting may take place on Saturdays only between 9 a.m. and 6 p.m.
  • Tree planting 
  • Dust monitoring and watering as necessary.
  • Vehicles and equipment moving through the site.

HOURS OF OPERATION & SCHEDULED ACTIVITIES (no new updates)

Construction takes place Monday through Friday from 7 a.m. to 6 p.m. daily. Equipment and machinery are turned on after 7:30 a.m. An update will be provided if work is required outside of this timeframe.

Please note plans, activities and onsite equipment are subject to change based on evolving project needs and weather.

NEED MORE INFORMATION? 

If you have any questions or comments about construction-related activities or would like to sign up to receive weekly updates by email, please contact [email protected].

Check out previous construction updates here.