Templeton Area Redevelopment Update

Construction Activities: Week of June 28, 2021

Site work for the Templeton Area Redevelopment continues, with ongoing construction of the Templeton Corridor. Construction activity for this corridor is nearing completion, with paving to be completed on Monday, followed by installation of new fencing next week, then landscaping this fall when the cooler weather returns. Learn more about what to expect during construction here. This week's update follows below.

Thank you to all our neighbours for your support and patience as we work to complete this project safely and in a timely manner.

GENERAL INFORMATION (new updates this week)

Paving will be completed today. Other work this week focuses on remaining sidewalk preparation and lamppost installations. Crews will not work July 1 or 2. For notice of other activities this week, please see detailed update below. 

If you have questions about the project and would like to connect with our community liaison Pam by phone or in person, please email to [email protected] or call 604-561-2836.

WEEK OF JUNE 28, 2021: WHAT YOU CAN EXPECT 

Areas of focus this week (all weather dependent) include:

New this week:

  • Sidewalk preparation
  • Lighting installation (deferred from last week).

Continuing this week:

  • Paving (Tuesday). 
  • Ground stripping to widen the existing path between Aylmer Road and Sea Island Station.
  • Dust monitoring and watering as necessary. 
  • Drainage monitoring.
  • Vehicles and equipment moving throughout the site.

Onsite equipment includes excavators, backhoe loaders, haul trucks, concrete trucks, compacting equipment, a forklift and a mobile crane. Broadband travel alarms are in use on regularly stationed equipment to reduce noise in the area. Traditional tonal alarms may still be heard on equipment and vehicles that travel to and from the site, or equipment that will be onsite for shorter durations.

HOURS OF OPERATION & SCHEDULED ACTIVITIES

Construction takes place Monday through Friday from 7 a.m. to 6 p.m. daily. Equipment and machinery are turned on after 7:30 a.m and most work is complete before sunset. An update will be provided if work is required outside of this timeframe.

Please note plans, activities and onsite equipment are subject to change based on evolving project needs and weather. Given the increased frequency of rain, workers may need to come to the site to monitor erosion and ensure the proper flood protections are performing adequately outside of the normal hours of operation.

NEED MORE INFORMATION? 

If you have any questions or comments about construction-related activities, please contact [email protected].

Check out previous construction updates here.