Construction Activities: Week of January 11, 2021

Site work on the Templeton Area Redevelopment continues, with ongoing construction of the Templeton Corridor. Construction activities for this phase are scheduled to take place through mid-2021. Learn more about what to expect during construction here. This week's update follows below.

Thank you to all our neighbours for your support and patience as we work to complete this project safely and in a timely manner.

GENERAL INFORMATION (new updates this week)

Rainfall over the past several weeks has subsided and crews can now begin removing preload from the area that will become the Terrace Road extension. This means residents can expect to see and hear construction trucks and equipment throughout the site for the next two weeks. See below for this week’s update.

If you have questions about the project and would like to connect with our community liaison Pam by phone or in person, please email to [email protected].

WEEK OF JANUARY 11, 2021: WHAT YOU CAN EXPECT 

Areas of focus this week (all weather dependent) include:

Starting this week:

  • Remove preload material from the future Terrace Street extension. Preload will be distributed throughout the site.
  • Gravel placement for effective drainage in areas where the future design calls for swales to create focused drainage within YVR lands.

Continuing:

  • Soil grading and old utility removals, primarily in western half of the site.
  • Monitoring the temporary trench to help address flooding in the laneway behind Wellington Crescent as the City of Richmond develops a permanent drainage solution.

Onsite equipment includes excavators, backhoe loaders, haul trucks, concrete trucks, compacting equipment, a forklift and a mobile crane. Broadband travel alarms are in use on regularly stationed equipment to reduce noise in the area. Traditional tonal alarms may still be heard on equipment and vehicles that travel to and from the site, or equipment that will be onsite for shorter durations.

HOURS OF OPERATION & SCHEDULED ACTIVITIES

Construction takes place Monday through Friday from 7 a.m. to 6 p.m. daily. Equipment and machinery are turned on after 7:30 a.m. An update will be provided if work is required outside of this timeframe.

Please note plans, activities and onsite equipment are subject to change based on evolving project needs and weather. Given the increased frequency of rain, workers may need to come to the site to monitor erosion and ensure the proper flood protections are performing adequately outside of the normal hours of operation.

NEED MORE INFORMATION? 

If you have any questions or comments about construction-related activities, please contact [email protected].

Check out previous construction updates here.