Templeton Area Redevelopment Update

Construction Activities: January 17, 2022

With remaining work on the project all being low impact, weather-dependent activity, YVR will now provide updates when milestone events have been reached rather than weekly or bi-weekly. For more information on remaining work, please see the table below. We continue to welcome questions at any time at [email protected].

OVERVIEW 

Landscaping, tree planting and final irrigation system installs in the meadow areas continue, to complete the project. All work takes place weather permitting. For notice of specific activities related to the Templeton Project please visit our construction update page.

Please note that the park remains closed to the public until construction is complete and plantings take root. The area is open for YVR authorized wildlife personnel only.

CONSTRUCTION ACTIVITY: WHAT YOU CAN EXPECT  

  • Landscaping and tree planting
  • Minor concrete work throughout
  • Pedestrian sign installs
  • Road line painting
  • Vehicles and equipment moving through the site

HOURS OF OPERATION & SCHEDULED ACTIVITIES

Construction takes place Monday through Friday from 7 a.m. to 6 p.m. daily. Equipment and machinery are turned on after 7:30 a.m. An update will be provided if work is required outside of this timeframe. No work will take place on weekends or statutory holidays.

NEED MORE INFORMATION? 

If you have any questions or comments about construction-related activities or would like to sign up to receive weekly updates by email, please contact [email protected].

For more information or general questions about the Templeton Area Redevelopment Project, please visit yvr.ca/templeton.