We are continuing site preparation work and construction of the Templeton Corridor.

This next phase of work will commence the week of March 16, 2020 and we expect it to be completed by the end of January 2021.

We received valuable input throughout the community engagement process for the Templeton Redevelopment project, which helped shape the design for the Templeton Corridor and other project requirements.

The enhanced Templeton Corridor will include the addition of hundreds of new plantings and greenspace with a variety of new areas to enjoy—from naturalized meadows to flexible and active open space, seating areas, trails and multi-use pathways connecting to the greater Sea Island network. Lighting will be added to the multi-use paths and we will replace the fence between YVR property and Burkeville. The field next to Little Wings Daycare will be leveled and landscaped with improved drainage. We will also narrow Templeton Street and construct Terrace Street extension. The contractor will also install various utilities for the future development.

Alternate Routing

To ensure a safe work environment is maintained, the project site will be fenced off with no public access to the area. Public vehicles are not permitted south of Sea Island Elementary School. During this phase of work, pedestrians and cyclists will be detoured around the project site.

  • Access to Templeton Street, south of Sea Island School, will be closed to all pedestrians and cyclists.
  • The south access point at Wellington Crescent will be closed.
  • Access from Aylmer Road through to Templeton Street will also be closed.

Project Snapshot – What to Expect*

All work is scheduled to take place within the City of Richmond by-laws, Monday through Friday from 7 a.m. to 6 p.m. daily. Noisier work will take place between 7:30 a.m. and 5:00 p.m. In the event that weekend work is required, we will provide an update.

March 2020

  • Demolition and clearing works along Templeton Street and Terrace Street
  • Installation of temporary site fencing

April to June 2020

  • Pre-load installation along Terrace Street and a short section on the west side of Templeton Street (pre-loads will be sand or gravel fill piles up to approximately 2 metres above finished road grades)
  • Fencing modifications around the site
  • Utilities installation including storm drainage, water, communications and electricity
  • Commence road and multi-use path construction

July 2020 to January 2021

  • Remove pre-loads
  • Complete utilities installations and road and multi-use path construction
  • Installation of hard and soft landscaping
  • Installation of roadway lighting and a new signalized intersection at Aylmer Road and Miller Road
  • Replacement of the existing fence between YVR property and Burkeville

*All plans are subject to change based on evolving project needs and weather.

We appreciate your patience while we complete this work. We will continue to provide updates on this project at yvr.ca/constructionupdates.

Questions?

If you have any questions or comments about construction related activities, please contact [email protected].

For more information or general questions about the Templeton Area Redevelopment Project, please visit yvr.ca/engagement/templeton.

We use cookies to improve user experience, and by using this site, you consent to the use of cookies. Learn more and how to manage your preferences on our Privacy page.