Skip to main content

Floodbox replacement on Inglis Drive

YVR is removing and replacing Flood Box E (i.e., the drainage system) off Inglis Drive, which provides access to our South Terminal. This replacement will provide flood mitigation and increase climate resilience on Sea Island.

Inglis Drive road diversion map near the South Terminal

This project requires a temporary reconfiguration of Inglis Drive to ensure construction has complete access to the flood box and discharge pipes in the area.

Please be advised, the reconfigured roadway with a reduced speed limit of 30 km/h will open on the morning of August 8th, 2022 and will be in place until early 2023. We have a traffic management plan in place to ensure a smooth transition.

Proposed Schedule

Work on this project starts in the summer of 2022 and working hours are from 7 a.m.- 5 p.m. Completion of the project is scheduled for early 2023.

Construction Activities

To minimize the impact to operations, the contractor will be working within the construction site. Activities include:

  • Demolition and installation of a new flood box and outlet;
  • Constructing a new temporary roadway, and pedestrian/bike lanes on both sides of the road; and
  • Returning the roadway to the original state.

We thank you for your patience getting to the South Terminal while we conduct this work.

We use cookies to improve user experience, and by using this site, you consent to the use of cookies. Learn more and how to manage your preferences on our Privacy page.